Plasterboard ceiling installation process

1. Before the formal construction, the worker first uses the horizontal pipe to measure the level of the ink line on the wall surface. Only when the actual level of the foundation line is guaranteed, the suspended ceiling installed later will not be tilted or there will be gaps.

2. The gypsum board ceiling needs to be fixed on a firm wooden keel frame, so careful selection of the keel material has become an indispensable step before. It is recommended that you try to choose the pine wood material that holds the nail strength better.

3, because the keel is wooden, so we must pay attention to fire prevention, the standard practice is that the surface of the keel evenly painted fireproof coating, etc., the whole keel is white, and then nailed to the wall, which can ensure its place of contact with the wall Also brushed into fireproof paint.

4. After the surface of the keel has been fireproofed, the combination can begin. The worker will use a nail gun to fix the two keels at an angle of 45 degrees diagonally. At this time, it is necessary to master the strength to prevent the keel from cracking.

5. After fixing the keel frame, it is necessary to fix the frame on the wall. At this time, it is necessary to carefully check whether the spacing between the frames is not more than 300 mm to have sufficient fastness. Otherwise, the gypsum board on it easily sinks and breaks.

6, the next step is to formally plasterboard, it is best to allow workers to use drywall screws stainless steel fixed gypsum board, such nails will not rust, the future can guarantee the gypsum board a long time beautiful.

7, nail holes on the gypsum board will usually be treated with rust nail putty, and its practical cement to fill the nail is a more cost-effective way. And the effect after the treatment is not worse than nail eye putty.

8. The gaps between the two plasterboards must be handled in the next step, otherwise there will be obvious cracks in the future. General workers will use 901 glue and gypsum powder after mixing.

9, after filling the cracks with gypsum powder, it is best to use anti-crack tape on the surface to prevent cracking caused by thermal expansion and contraction. When sticking, pay attention to the use of a spatula to remove the air bubbles on one side and allow the tape and plasterboard to be completely and tightly combined.

10, for the special shape of the ceiling, the post-processing is very important. The ceilings, such as circular and wavy, all require experienced masters to repair them slowly with a spatula. This is the most important process for forming the entire ceiling.

11. After the basic shape has been repaired, the edge of the ceiling shall be sanded again and the edges and edges of the edges shall be removed. Must be patient and careful when handling, otherwise it will affect the appearance in the future.

12. After several days of hard work, the ceiling of the home can be completed. As long as the key links in the above several constructions are well grasped, the appearance and safety of the gypsum board ceilings can be guaranteed.

Ceiling Mounted Coating Cement Stainless Steel

4 Person Hot Tub

4 Person Hot Tub

4 Person Hot Tub,home outdoor spa,outside jacuzzi pool,round hot tub,garden hot tubs

Guangzhou Aijingsi Sanitary Products Co.,Ltd , https://www.hottubdesign.com